Tier 1 Critical

WECCO

📍 10622 WEST 6400 NORTH, CEDAR CITY, UT 84720🏭 Manufacturing (NAICS 325188)📅 2002-04-12
$145,230.00
Total Penalties
62
Citations
85/100
Risk Score
397
Analysis Words
Enforcement Analysis

According to U.S. Department of Labor enforcement records, WECCO — a manufacturing facility located at 10622 WEST 6400 NORTH, CEDAR CITY, UT 84720 — was the subject of a formal OSHA inspection that resulted in 62 citation(s) and cumulative proposed penalties of $145,230.00. The inspection case was opened on 2002-04-12.

This facility represents one of the most severe enforcement actions in the OSHA SVEP database. Willful violations combined with penalties exceeding $100,000 indicate a pattern of deliberate non-compliance that poses an imminent danger to workers.

Industry Benchmark: The total penalty of $145,230.00 is more than 17.3× the national average of $8,414.32 for facilities in the Manufacturing sector (NAICS 325188). This sector encompasses 52,095 inspected facilities nationwide with aggregate penalties totaling $438.3M.

State Context: Within UT, this facility's penalty places it at the 100th percentile among 21,375 inspected facilities. The statewide average penalty is $1,557.94.

Citation Analysis: The inspection produced 62 citations spanning 6 distinct OSHA regulatory standards. The citation breakdown includes: 6 willful — The employer intentionally and knowingly committed the violation, demonstrating either an intentional disregard for the requirements of the OSH Act or plain indifference to employee safety and health. 8 serious — A workplace hazard that could cause death or serious physical harm exists, and the employer knew or should have known about the condition. 1 other-than-serious — The violation has a direct relationship to job safety and health but is unlikely to cause death or serious physical harm.

Enforcement Timeline: Citations were issued beginning October 10, 2002 with the latest abatement deadline set for November 12, 2002. Of the 62 total citations, 15 (24%) have been marked as abated in DOL records, which may indicate ongoing compliance gaps requiring further regulatory attention.

Penalty Assessment: The cumulative penalty of $145,230.00 reflects OSHA's gravity-based penalty calculation methodology, which considers the severity of potential injury, the probability of occurrence, the employer's size, good faith, and violation history. The per-citation average of $2,342.42 falls within the standard penalty range.

The inspection of WECCO’s Cedar City facility revealed a catastrophic breakdown of Process Safety Management

Citation Matrix — 62 Citations
29 CFR 1910.119(g)(01)
Process Safety Management
Willful
Penalty: $22,750.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.119(j)(06)
Process Safety Management
Willful
Penalty: $22,750.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.134(d)(01)
Fall Protection — General Requirements
Serious
Penalty: $2,275.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.134(k)(05)
Fall Protection — General Requirements
Willful
Penalty: $2,275.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.1025(d)(06)
Willful
Penalty: $2,275.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.1025(e)(03)
Serious
Penalty: $22,750.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.1025(m)(02)
Other-than-Serious
Penalty: $0.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.119(f)(01)
Process Safety Management
Willful
Penalty: $22,750.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.242(b)
Willful
Penalty: $0.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.304(f)(04)
Electrical — Wiring Design & Protection
Serious
Penalty: $0.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
OSHA Std. 10005 D04
Serious
Penalty: $2,275.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.23(c)(01)
Guarding Floor & Wall Openings
Serious
Penalty: $2,275.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.119(d)(03)
Process Safety Management
Serious
Penalty: $2,275.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.119(e)(05)
Process Safety Management
Serious
Penalty: $2,275.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
29 CFR 1910.119(j)(05)
Process Safety Management
Serious
Penalty: $2,275.00Gravity: nanIssued: October 10, 2002Abated: ✓ Yes
This report is compiled from publicly available U.S. Department of Labor enforcement data under the Freedom of Information Act. SVEP Navigator is an independent research and analysis platform and is not affiliated with, endorsed by, or connected to OSHA, the Department of Labor, or any federal agency. Information is provided for research, educational, and compliance planning purposes only and does not constitute legal advice. Penalty amounts shown are proposed penalties and may have been modified through contest proceedings or settlement.
More UT Enforcement Records
US MAGNESIUM LLC
GRANTSVILLE, UT
$1.2M
72 cit.
SILVER EAGLE REFINING INC
WOODS CROSS, UT
$584.5K
75 cit.
GENEVA STEEL
OREM, UT
$252.6K
215 cit.
KENNECOTT UTAH COPPER
MAGNA, UT
$239.4K
58 cit.
DEL RAY JACKSON CONSTRUCTION
ST GEORGE, UT
$213.5K
12 cit.